Brookfield and NextEra Paducah campus (Kentucky)

Brookfield and NextEra Energy plan a data center campus of over 1.2 GW at the DOE Paducah Site in Kentucky.

Owner
Brookfield, NextEra Energy
Partners
U.S. Department of Energy (site), Big Rivers Electric, Jackson Purchase Energy Cooperative, Paducah Power System
Location
DOE Paducah Site, western Kentucky
Announced capacity
1,200 MW
Capacity as announced
Over 1.2 GW of compute capacity; up to 4.6 GW of dedicated generation
Status
Announced
Timeline
Construction complete by 2032; subject to definitive agreements
Announced

On July 29, 2026, NextEra Energy announced a data center campus with Brookfield at the U.S. Department of Energy’s Paducah Site in western Kentucky, with over 1.2 GW of compute capacity. The plan pairs the campus with up to 4.6 GW of dedicated generation: up to 2 GW of natural gas and up to 2.6 GW of battery storage. The companies put the privately funded investment at $100 billion, with construction to be completed by 2032.

NextEra said the project is subject to negotiation and execution of definitive documentation; Big Rivers Electric, Jackson Purchase Energy Cooperative and Paducah Power System are named as partners.

Country
United States
Project type
Data center campus
Announcement
newsroom.nexteraenergy.com
Checked

Questions

How big is the Brookfield and NextEra Paducah data center campus?
The campus is planned with over 1.2 GW of compute capacity and up to 4.6 GW of dedicated generation.
How much will the Paducah data center campus cost?
The companies put the privately funded investment at $100 billion.
When will the Paducah campus be finished?
Construction is to be completed by 2032; the project is subject to negotiation and execution of definitive documentation.
What power will the Paducah campus use?
The plan pairs it with up to 2 GW of natural gas generation and up to 2.6 GW of battery storage.
Sources:
NextEra Energy newsroom, July 29, 2026. Checked October 2, 2026.