TeraWulf Muskie Data Campus: contracted power raised to 1 GW (Kentucky)
TeraWulf doubled contracted power at its Muskie Data Campus in eastern Kentucky to 1 GW under an amended agreement with Kentucky Power.
- Owner
- TeraWulf
- Partners
- Kentucky Power (AEP)
- Location
- Muskie Data Campus, eastern Kentucky
- Announced capacity
- 1,000 MW
- Capacity as announced
- Contracted power raised from 500 MW to 1 GW; up to 2 GW under evaluation
- Status
- Contracted
- Timeline
- Phase 1 (500 MW) ramps from 2028; phase 2 moved to 2029, subject to Kentucky PSC approval
- Announced
On October 5, 2026, TeraWulf announced an amended and restated electric service agreement with Kentucky Power, an American Electric Power company, that raises contracted power at its Muskie Data Campus in eastern Kentucky from 500 MW to 1 GW. The first 500 MW phase remains targeted to begin ramping in 2028, and the amendment advances planned delivery of the second 500 MW phase from 2030 to 2029, subject to Kentucky Public Service Commission approval and Kentucky Power’s construction schedule. Kentucky Power is building a 765-kV/345-kV substation for the site. TeraWulf, which acquired Muskie in May 2026, said it is evaluating the campus’s potential to support up to 2 GW over time; it named no tenant.
- Country
- United States
- Project type
- Power deal
- Announcement
- investors.terawulf.com
- Checked
Questions
How much power is contracted at TeraWulf’s Muskie campus?
When will the Muskie Data Campus come online?
Does the Muskie expansion need regulatory approval?
Sources:
Source
Every value comes from the company’s own announcement, investor release or newsroom post, linked on each project with the date it was last checked. How we pick and check sources: editorial standards.