xAI Colossus supercomputer (Memphis, Tennessee)
xAI’s Colossus supercomputer is in Memphis, Tennessee.
- Owner
- xAI
- Partners
- MLGW and TVA (utilities)
- Location
- Memphis, Tennessee
- Capacity as announced
- xAI states 200,000 GPUs; no power capacity stated
- Chips
- NVIDIA H100 and other NVIDIA GPUs
- Status
- Operational
- Timeline
- Built in 122 days, then doubled in 92 days; xAI states a roadmap to 1 million GPUs
xAI’s Colossus page says the system reached 200,000 GPUs, was built in 122 days and then doubled in 92 days, with 170 PB/s of total memory bandwidth, 2.8 Tb/s of network bandwidth per server and more than 0.5 EB of storage, and it describes a roadmap to 1 million GPUs. xAI’s Memphis page names MLGW and TVA as its utilities. Neither page states a power capacity. Our explainer: xAI Colossus.
- Country
- United States
- Project type
- Data center campus
- Announcement
- x.ai
- Checked
Questions
How many GPUs does xAI Colossus have?
xAI states 200,000 GPUs and a roadmap to 1 million.
How long did Colossus take to build?
xAI says it was built in 122 days and doubled in another 92 days.
Where is Colossus?
In Memphis, Tennessee, served by MLGW and TVA.
Source
Every value comes from the company’s own announcement, investor release or newsroom post, linked on each project with the date it was last checked. How we pick and check sources: editorial standards.