AI data center power consumption is measured at three levels: a rack in kilowatts, a campus in megawatts or gigawatts, and a country in terawatt-hours a year. One Nvidia GB200 NVL72 rack draws about 120 kW, according to Nvidia’s user guide, and Microsoft runs its Fairwater racks at about 140 kW. Nvidia and Google are now preparing racks of up to 1 MW each, which Nvidia plans to support from 2027.
Those AI racks already sit above the 10 to 100 kW range that Google says the older 48-volt rack design was built for. At campus scale, announcements reach OpenAI’s approximately 8 GW-IT PORTS-Pike site in Ohio, and a Lawrence Berkeley National Laboratory report for the US Department of Energy found that data centers used about 4.4% of US electricity in 2023.
Last checked November 12, 2026. Figures come from vendors’, operators’, utilities’ and agencies’ own publications.
On this page
Rack level: from 14 kW servers to 1 MW racks
The smallest unit with a published power figure is the server. Nvidia’s DGX B200 user guide gives a maximum system power of 14.3 kW for one 10U system with eight B200 GPUs.
Rack-scale systems put far more GPUs in one cabinet. Nvidia’s GB200 NVL72 is a single liquid-cooled rack with 72 Blackwell GPUs and 36 Grace CPUs. Nvidia’s DGX GB200 user guide says the rack’s power consumption is “approximately 120kW”, fed by eight power shelves of six 5.5 kW supplies each, with 33 kW of input power per shelf. Microsoft, which runs Blackwell racks in its Fairwater data centers, said in November 2025 that the Fairwater design operates at about 140 kW per rack and 1,360 kW per row. The rack itself is covered in GB200 NVL72 explained.
| System or design | Power figure | Who says so | Status |
|---|---|---|---|
| 48 VDC in-rack power (Google’s earlier standard) | 10 kW to 100 kW per rack | Google, April 29, 2025 | Current design range |
| Nvidia DGX B200 server (8 GPUs) | 14.3 kW maximum per system | Nvidia DGX B200 user guide | Shipping |
| Nvidia DGX GB200 NVL72 rack (72 GPUs) | About 120 kW per rack | Nvidia DGX GB200 user guide | Shipping |
| Microsoft Fairwater rack and row | About 140 kW per rack; 1,360 kW per row | Microsoft, November 12, 2025 | Operating |
| Google +/-400 VDC power rack (Mt Diablo) | Up to 1 MW per rack | Google, April 29, 2025 | Specification with Meta and Microsoft at OCP |
| Nvidia 800 VDC row power center | Up to 2 MW per row | Nvidia, August 11, 2026 | Expected 2027 |
| Nvidia 800 VDC racks, Kyber with 576 Rubin Ultra GPUs | “1 MW IT racks and beyond” | Nvidia, May 20, 2025 | Starting 2027 |
Google gave its own forecast for where rack power is heading: machine learning “will require more than 500 kW per IT rack before 2030.”
Why megawatt racks need new power delivery
Today’s racks take AC power and convert it to about 50 volts DC inside the rack. Nvidia’s user guide describes the GB200 NVL72 power shelves doing exactly that, converting AC to “nominal 50V-51V DC” on a bus bar. Nvidia says this approach does not scale to a megawatt. At 54 VDC, a single 1 MW rack would need up to 200 kg of copper busbar, and the power shelves for a megawatt Kyber rack would take up to 64U of rack space, leaving no room for compute.
The answer from both companies is a higher voltage, with power conversion moved out of the IT rack into a separate “sidecar” rack or to the facility. Google’s version is +/-400 VDC, chosen partly to use the electric-vehicle supply chain; it says its first sidecar improves end-to-end efficiency by about 3%. Nvidia’s is 800 VDC, which it says carries 85% more power through the same conductor size than 415 VAC and improves end-to-end efficiency by up to 5% against 54 V systems. In August 2026 Nvidia said it, Google and Microsoft had been developing the 800 VDC architecture together through the Open Compute Project, and that more than 80 manufacturers were building to the specification.
A rack figure is IT power only. Cooling, power conversion and the rest of the building come on top, which is why a campus’s grid connection is larger than the sum of its racks.
Campus level: what the announced numbers measure
Data-center owners announce capacity in megawatts (MW) or gigawatts (GW), but not always the same quantity. Four meanings appear in announcements:
- IT load (MW-IT, GW-IT, “critical IT capacity”). Power available to the servers, storage and network equipment. It excludes cooling and electrical losses.
- Power or utility load. What the site draws from the grid, which covers IT load plus cooling and other building systems.
- Compute capacity. A term some owners use without saying which of the two above it means.
- MWe and contracted generation. The electrical output of a power plant, or the share of it a buyer has contracted under a power purchase agreement (PPA). This is supply, not data-center demand, and the power may serve operations across a grid region rather than a single campus.
One contract shows the gap between the first two. On September 30, 2026, AIB Data Centers said it had agreed to provide Nebius with “50 MW of critical IT capacity” in the southeastern United States, at a site supported by “a 15-year Electric Service Agreement for 65 MW of utility load.” The same facility is described by both numbers.
| Project | Announced figure | What the figure measures | Owner’s timeline |
|---|---|---|---|
| OpenAI PORTS-Pike, Ohio | About 8 GW-IT | IT load | First 800 MW in 2028; buildout through 2032 |
| Meta Richland Parish, Louisiana | 5 GW | “Compute capacity” | Expansion announced July 13, 2026 |
| OpenAI Project Camellia, Georgia | 3.2 GW | Power delivered by Georgia Power | Phases between 2028 and 2032 |
| NextEra and Brookfield, Paducah, Kentucky | Over 1.2 GW | Compute capacity, with up to 4.6 GW of dedicated generation | Fully built in 2032; subject to definitive agreements |
| xAI Colossus, Paul R. Lowry Road, Memphis | 150 MW, with a second 150 MW requested | Grid power delivered by MLGW and TVA | 150 MW in service by May 2025; second increment pending TVA approval at that date |
| AIB Data Centers for Nebius | 50 MW | Critical IT capacity (65 MW utility load) | 12-year initial term |
| Constellation and Amazon, Calvert Cliffs | 690 MW | Contracted nuclear generation (PPA) | 20 years; about 190 MW of uprates online 2030–2032 |
| Crusoe and Aalo Atomics, Idaho | 10 MWe | Reactor electrical output (Aalo-X) | Proof of concept at Idaho National Laboratory in 2027 |
The Colossus figure comes from the utility, not from xAI. Memphis Light, Gas and Water said on May 5, 2025 that the site was receiving 150 MW from the TVA/MLGW grid (8 MW from an existing substation and 142 MW from a new one), that xAI had asked for a second 150 MW for 300 MW in total, and that it expected to supply the second increment by no later than December 2025 if TVA approved it. The xAI Colossus explainer covers the site’s turbines, batteries and later expansion.
Company-wide totals use yet another basis. CoreWeave said on September 17, 2026 that its “total contracted power” was approximately 4.2 GW as of August 11, 2026, a figure for the company as a whole rather than for a single building. The AI data centers tracker records every project with the capacity wording its owner used.
Why a gigawatt figure is not annual consumption
Capacity is a rate; consumption is energy over time. As a simple illustration, 1 GW drawn continuously for a full year would be 8.76 TWh (1 GW × 8,760 hours). Real campuses come online in phases over several years and do not run at full capacity every hour, so an announced gigawatt figure says little about a given year’s electricity use. PORTS-Pike, for example, starts with 800 MW in 2028 and reaches its full size only by 2032, according to OpenAI.
The same arithmetic links racks to campuses. Divided by Nvidia’s figure of about 120 kW per GB200 NVL72 rack, 100 MW of IT load would be roughly 830 such racks, before any power for cooling. This is our calculation, not a vendor figure, and real halls mix racks, networking and storage.
National statistics: the US DOE and LBNL report
The main official US estimate is the United States Data Center Energy Usage Report by Lawrence Berkeley National Laboratory, released by the Department of Energy on December 20, 2024. The DOE summary gives these figures:
- US data centers used about 58 TWh in 2014 and 176 TWh in 2023.
- That 2023 figure was about 4.4% of total US electricity consumption.
- The report projects 325 to 580 TWh by 2028, or about 6.7% to 12% of US electricity.
- Data-center load “has tripled over the past decade” and is “projected to double or triple by 2028.”
The report covers all data centers, not only AI facilities.
Global statistics: the IEA
The International Energy Agency’s Energy and AI report, published April 10, 2025, puts global data-center electricity consumption at around 415 TWh in 2024, about 1.5% of the world’s electricity use. The IEA projects that this will “more than double to around 945 TWh by 2030,” with electricity demand from AI-optimized data centers projected to more than quadruple over the same period.
The IEA also gives a scale comparison: “A typical AI-focused data centre consumes as much electricity as 100 000 households, but the largest ones under construction today will consume 20 times as much.” For the United States, it projects that data centers will account for almost half of the growth in US electricity demand between the report’s publication and 2030.
Reading power claims
When a company announces a gigawatt-scale AI data center, three questions help place the number: whether it is IT load, grid power or contracted generation; whether it is the first phase or the full build; and what year the owner expects it to be online. For a rack, the question is whether the figure is a shipping system’s measured consumption (about 120 kW for a GB200 NVL72) or the ceiling a future power design is built for (1 MW). The official statistics answer a different question, total energy used across all data centers in a year, and the two kinds of figure should not be compared directly. Power deals that supply these campuses, including the Constellation and Amazon Calvert Cliffs agreement, are counted in generation, not demand. How AI halls differ from conventional ones in cooling and layout is covered in AI data center vs traditional data center.





